Ppwer: NISO, WAPP complete synchronization test on West African single grid
2 min read
By Chris Ochayi
The Nigerian Independent System Operator (NISO), in collaboration with the West African Power Pool Information and Coordination Centre (WAPP-ICC), have successfully carried out the long-awaited synchronization test between the Nigerian power grid which includes Niger Republic and parts of Benin and Togo and the rest of the West African power grid.
This development was contained in a statement signed by the Chairman Board of Directors, Dr. Adesegun Akin-Olugbade, and the Managing Director and Chief Executive Officer of NIISO Engr Abdu Bello Mohammed respectively
The statement noted, “The test was conducted on Saturday, 8th November 2025, between 05:04 hours and 09:04 hours, and marks a major breakthrough in the ongoing effort to establish a unified West African electricity grid operating at a single frequency.”
“Although several synchronization arrangements had been proposed in the past, the only known physical synchronization attempt took place in 2007 and lasted for about seven minutes before being discontinued.
“Following renewed engagements and enhanced coordination between NISO and the WAPP-ICC, the exercise has now been successfully accomplished through improved system monitoring, stricter frequency control, harmonized operational standards, and real-time communication among participating control centres.
“The synchronization connects Area 1 (Nigeria, Niger, and parts of Benin and Togo) with Areas 2 and 3 (the rest of West Africa), creating a single operational grid that enhances reliability, stability, and cross-border energy exchange across the ECOWAS region.
“The initiative aims to achieve operational unification of the regional grid, improve system reliability through shared reserves, enable cost-effective power generation and trading under the West African Electricity Market (WAEM), and strengthen institutional cooperation among member system operators.
“For Nigeria, this achievement provides multiple benefits, including unlocking stranded generation capacity, enabling energy exports and foreign exchange earnings, improving grid resilience, and reinforcing the country’s leadership role in regional energy integration”, it said.
The statement stressed further that, “It also opens access to donor funding for priority transmission projects such as the North Core Project in Birnin Kebbi and the Ajegunle 330 kV Substation in Lagos State.
“The successful synchronization marks a historic milestone in regional energy cooperation and demonstrates NISO’s technical capacity to manage complex grid operations in line with international standards.”